June 13th
Pictures to come... With the help of Bill and Pam, we got the bathroom sub-floor in and starting some framing on sunday the 12th.
HVAC will begin tomorrow and should take around a week. During this time we will continue to do some framing before the plumber comes in.
I did some work in the back of the house... finished of the concrete work. We will level the small plot of dirt, or yard as some people call it, and just put some bricks down to create a walk way to the fence...
Now we just need to shim some of the joists, shim some areas of the floor between the joists and floor, and use some of the boards we took up for the bathroom subfloor and put them in the area of the kitchen which needs some boards where the old bathroom was.
Supporting stairs will be a task for another day... probably when we start framing out the wall under the stairs and putting the door in the kitchen, down to the basement